Case Studies
Development case study: MEM delivered a 1.39% increase in investor equity returns by optimizing contracting of a 60MW wind project.
FINANCE KPI | BASE | IMPROVEMENT | CHANGE |
---|---|---|---|
Construction | 142.46mUSD | 138.66mUSD | -3.8mUSD |
IDC | 3.8mUSD | 2.56mUSD | -1.24mUSD |
Total,CAPEX | 146.26mUSD | 141.22mUSD | -5.04mUSD |
IRR | 15.73% | 17.12% | 1.39% |
EXAMPLE:
60MW wind farm – MEM project team in contracting phase to improve project plan commercial contracting and payment milestones |
SUCCESS CRITERIA:
MEM team improved levered IRR to above 16% requirement |
Drivers:
|
Asset optimization case study: MEM identified revenue losses in a wind farm entering its second year of operations.
Performance Issue | Identified Energy Yield Loss | Annual Pro Rata Loss |
---|---|---|
Power Curve/De-rating the Power Output of WTGs | 335, 386kWh | 2,074,845kWh |
Incorrect Allocation of Downtime | 62.25hrs or 0.15% Availability | 0.93% Availability loss |
Key findings which MEM corrected included:
- Construction punch list (installation defects)
- Commissioning defects (air density and blade alignment of WTGs affecting output)
- O&M contractor misallocation of WTG down time